PRESS RELEASE: MN PUC grants Eminent Domain for Sandpiper, calls for Environmental Review and Cooperation with Tribes, Federal Agencies

On Monday, August 3, the Public Utilities Commission (PUC) issued two orders for Enbridge’s Sandpiper pipeline application – granting the Certificate of Need, which conveys to Enbridge the powers of eminent domain, and commencing the routing permit review process. However, there were conditions. First, the PUC order requires a thorough Comparative Environmental Analysis (CEA), which “shall also include a qualitative as well as quantitative analysis of the environmental impacts of the various route alternatives; and consider the environmental impact of the Sandpiper facility alone and the cumulative impact of both the Sandpiper facility in the Line 3 replacement project.” This is an important shift in regulatory process, as the PUC previously denied the motion by Honor the Earth to combine environmental analysis for Line 3 and Sandpiper (Map).